Angus Council The refurbishment of 300 Wimpey No-Fines homes carried out over three phases with funding from ECO, HEEPS (ABS) plus RSL contribution. Works commenced over three phases, phase 1 – July 2015 (55 properties), phase 2 – May 2016 (89 properties), phase 3 – November 2016 (250 properties).Project Length: Phase 1 – 3 months, phase 2 – 5 months, phase 3 – ongoing Client Angus Council, Private Homeowners Location Forfar, Arbroath, Montrose Start Date July 2015 Value £2,500,000 Length 13 Months Work Type External Wall Insulation, Internal Wall Insualtion, Electric Heating, Gas Boiler Upgrades, Window Replacement, Underfloor Heating Number of Properties 394 Type of Properties Wimpey No-Fines Insulation Type 90mm Grey EPS U Value Finish Applied Pebble Dash